Under construction

SHRIPAD RESIDENCYMahaRERA P53100002221

by Abhijit Vijaykumar Borgave

SURVEY NO 133 3 PLOT NO 20, Sangli Miraj Kupwad (M Corp.), 416416

Mar 2019
Possession
89.1%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Mar 2019) has passed with construction at 89.1%.

Official RERA facts

Registration
P53100002221
Status
Ongoing
Stage
Certificate Signed
Possession
March 2019
Construction
89.1% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Jul 2017
Floors
6

Buyer community

Connect with other buyers and owners of SHRIPAD RESIDENCY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SHRIPAD RESIDENCY. Real notes from real buyers beat any brochure.

Start a discussion