Shiv City CenterMahaRERA P53100017288

by Shiv City Center Joint Venture

S.No.35A/A1/1A Plot No.5 And 25, Wanlesswadi, 416415

Mar 2023
Possession
81.8%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Dec 2020, now proposed Mar 2023 per the RERA filing.
  • Possession date passed. The proposed possession date (Mar 2023) has passed with construction at 81.8%.

Official RERA facts

Registration
P53100017288
Status
Ongoing
Stage
Certificate Signed
Possession
March 2023originally December 2020
Construction
81.8% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Open Parkingnot started
Common Parkingnot started

Building & registration

RERA registered
Jul 2018
Floors
7

Buyer community

Connect with other buyers and owners of Shiv City Center โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Shiv City Center. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.