FIZA E GARIBNAWAZMahaRERA P53100022044

by TRINITY BUILDCON

605B AND 606, NEAR MASJID GARIBNAWAZ, 416416

Jun 2023
Possession
81.8%
Built
1
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Jun 2023) has passed with construction at 81.8%.

Official RERA facts

Registration
P53100022044
Status
New
Stage
Certificate Signed
Possession
June 2023
Construction
81.8% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Water conservation /Rain water harvestingdone
Electrical meter room, sub-station, receiving stationdone

Building & registration

RERA registered
Aug 2019
Floors
7

Buyer community

Connect with other buyers and owners of FIZA E GARIBNAWAZ โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching FIZA E GARIBNAWAZ. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.