PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

SHREE SIDDHIVINAYAK HEIGHTSMahaRERA P53100027420

by SURYAPRATAP PROMOTERS AND BUILDERS

561 B 22, VITA, 415311

Mar 2025
Possession
43.7%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~2 yrs. Originally promised Jun 2023, now proposed Mar 2025 per the RERA filing.
  • Possession date passed. The proposed possession date (Mar 2025) has passed with construction at 43.7%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2025 per the RERA filing.

Official RERA facts

Registration
P53100027420
Status
New
Stage
Certificate Signed
Possession
March 2025originally June 2023
Construction
43.7% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Landowner

SURYAPRATAP PROMOTERS AND BUILDERS, PRATAP PANDHARINATH PATIL, PRANAV PRATAP PATIL, NAINA PRASANNA PATIL, PRASHANT PRASURAM JADHAV, GAURI PRASHANT JADHAV

Possession extension history

  • EXT53100024380Revised to November 2024

    In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 83.33% allottees for purpose of extension of RERA registration period of the said project.

  • EXT53100017050Revised to May 2024

    Respected Sir/Madam, I am writing on behalf of Suryapratap Promoters and Developers, the developer responsible for the construction of the "Siddhivinayak Heights" project located at Vita, Sangli. We would like to bring to your attention the reasons for the delay in completing the construction and request an extension of the completion date until 30th May 2024. The delay in the completion of the project can be attributed to two significant factors, which have severely impacted our construction timeline: 1. Non-availability of CEO, Vita Municipal Council for approving sanctioned plan: Due to unforeseen circumstances, the Chief Executive Officer (CEO) of the Vita Municipal Council, who is responsible for approving the sanctioned plan for the "Siddhivinayak Heights" project, has been unavailable. The delay in obtaining the necessary approvals has halted the progress of the construction. We have diligently followed up with the concerned authorities, but the unavailability of the CEO has caused significant delays in the project timeline. 2. Labour problems because of the Covid-19 pandemic situation: The outbreak of the Covid-19 pandemic has had a profound impact on the construction industry, including our project. The lockdowns and restrictions imposed by the government to curb the spread of the virus had resulted in a shortage of laborers and disrupted the supply chain of construction materials. Despite our best efforts to mitigate the impact of the pandemic, the shortage of laborers and delayed material deliveries had hampered the construction progress. Considering the circumstances beyond our control, we kindly request an extension of the completion date for the "Siddhivinayak Heights" project until 31st May 2024. This additional time will allow us to overcome the challenges we have faced and ensure the completion of the project in accordance with the approved plans and regulations. We assure you that Suryapratap Promoters and Developers are fully committed to delivering the project within the extended timeline. We will take all necessary steps to expedite the construction process, engage additional resources, and ensure compliance with all relevant regulations. We understand the importance of adhering to the regulations set by Maha Rera Authority and assure you that we will provide regular updates on the progress of the construction. We look forward to a positive response from the MAHA RERA Authority. Thank you.

  • EXT53100027954Revised to March 2025

    We, M/s. Suryapratap Promoters and Builders, hereby declare the following with respect to the project Shree Siddhivinayak Heights bearing registration number. P53100027420 registered under MahaRERA. The delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, we received the Occupation Certificate (OC) on 26th March 2025 and we have initiated the process for the possession as well, hence we won't be required to upload consents. To provide assurance and facilitate a smooth completion process, we are closely monitoring the remaining activities, ensuring timely execution, and addressing any issues that may arise. This proactive approach aims to ensure a successful transition to occupancy. As a measure of assurance, we kindly request an extension until OC Date i.e - 26th March 2025, allowing us to complete all necessary procedures and meet our commitments to stakeholders while ensuring compliance with applicable regulations

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Dec 2020
Floors
7
Plot / CTS / survey no.
561 B 22
Planning authority
Others
Approved layout land
1,093 sq.m
Land for this registration
1,093 sq.m
Permissible built-up area
1,973.54 sq.m
Registered office
NEHA CRYSTAL
Plot boundaries
North
MUNCIPAL ROAD
South
BUILDING OF GOLD TOWER
East
561 B 23
West
561 B 21
Parking

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • SARASWAT COOPERATIVE BANK LIMITED โ€” 143239
    IFSC SRCB0000183
    SHIVAJI CHOWK VITA

Commencement Certificate documents

  • commencement certificate Suryapratap.pdf
  • CENTRAL REVISED PERMISSION CERT_230805_095613.pdf

Buyer community

Connect with other buyers and owners of SHREE SIDDHIVINAYAK HEIGHTS โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SHREE SIDDHIVINAYAK HEIGHTS. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.