PRAJAKTAMahaRERA P53100028154
FINAL PLOT NO 30B, GAON BHAG, 416416
- Possession date passed. The proposed possession date (Jul 2023) has passed with construction at 55.5%.
Official RERA facts
- Registration
- P53100028154
- Status
- New
- Stage
- Certificate Signed
- Possession
- July 2023
- Construction
- 55.5% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 23 Jul 2026).
Landowner
PRAKASH KASHINATH APTE, AVINASH KASHINATH APTE, SHIRISH KASHINATH APTE
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Feb 2021
- Floors
- 5
- Plot / CTS / survey no.
- FINAL PLOT NO 30B
- Planning authority
- Others
- Approved layout land
- 158.92 sq.m
- Land for this registration
- 158.92 sq.m
- Permissible built-up area
- 309.62 sq.m
- Registered office
- BHAGWANT GROUP
- North
- PLOT NO 30A AND C S NO 1120-3AND 1120-4 AND 1120-5
- South
- 15 FEET ROAD
- East
- PLOT NO 36
- West
- PLOT NO 30 A
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- PUNJAB NATIONAL BANK โ 101138IFSC PUNB0140210DIWAN NIKETAN ,313,NEAR ST STAND SANGLI
Commencement Certificate documents
- COMENCEMENT CERTIFICATE.pdf
Buyer community
Connect with other buyers and owners of PRAJAKTA โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching PRAJAKTA. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.