SHAKTI APARTMENTMahaRERA P53100029574
122/3/1, KABAJ PLOT NEAR RAMKRISHNA PARMHANS SOCIETY, 416416
- Possession date passed. The proposed possession date (Aug 2022) has passed with construction at 90.9%.
Official RERA facts
- Registration
- P53100029574
- Status
- New
- Stage
- Certificate Signed
- Possession
- August 2022
- Construction
- 90.9% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 23 Jul 2026).
Landowner
DEEPAK GANESH PETKAR, Ratan Vishwanath Yadav
Possession extension history
- EXT53100012793Revised to March 2023
The said project work could not be done on the time due to local labor and material problems. The said project is progressing towards the direction of completion. We estimate that it will take another 7 months to complete whole work. Due to completion date we have given before, we are facing difficulty for documentary work required for progress of said project. So I request you to give extension for above mentioned project. We assure that, we will complete said project in that period absolutely
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Jun 2021
- Floors
- 4
- Plot / CTS / survey no.
- 122/3/1
- Planning authority
- Others
- Approved layout land
- 291.1 sq.m
- Land for this registration
- 291.1 sq.m
- Permissible built-up area
- 366.3 sq.m
- Promoter contact
- DEEPAK GANESH PETKAR
- Registered office
- ASHRAY SOCIETY
- North
- SURVEY NUMBER 423
- South
- 9 METRE WIDE ROAD
- East
- SURVEY NUMBER 425-3 PLOT NUMBER 2
- West
- 15 METRE WIDE ROAD
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- BANK OF INDIA โ 15506IFSC BKID0001507NEAR GANPATI TEMPLE VISHRAMBAG
Commencement Certificate documents
- Shakti Commencement Certificate.pdf
Buyer community
Connect with other buyers and owners of SHAKTI APARTMENT โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching SHAKTI APARTMENT. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.