- Possession date passed. The proposed possession date (Sept 2024) has passed with construction at 81.8%.
Official RERA facts
- Registration
- P53100047420
- Status
- New
- Stage
- Certificate Signed
- Possession
- September 2024originally July 2024
- Construction
- 81.8% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Landowner
YOGESH MAHADEV GALANDE, PRASHANT PRAKASH SURYWANSHI
Possession extension history
- EXT53100024943Revised to September 2024
Our project completion date was 31-07-2024. But there were some changes in our plan. Due to shortage of some material and labor, our project has been completed on 07-09-2024.Accordingly, we had submitted the construction completion certificate but as our date of 31-07-2024 has expired, we have been asked to get the extension up to 31.12.2024. and then upload it again. we are requested to get an extensionBut it is being told by you that you should take the extension till 07-09-2024. And correct the same in the application. But your system doesn't take this back date. However we need to change that date there and accept our certificate.
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Oct 2022
- Floors
- 6
- Plot / CTS / survey no.
- 85/1/A/2/1
- Planning authority
- SMKC
- Approved layout land
- 522.6 sq.m
- Land for this registration
- 522.6 sq.m
- Permissible built-up area
- 522.6 sq.m
- Registered office
- PARIJAT COLONY
- North
- S NO 177B
- South
- 9 MTRS ROAD
- East
- PLOT NO 11
- West
- PLOT NO 09
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- UNION BANK OF INDIA โ 148682IFSC UBIN0563986SANGLI
Commencement Certificate documents
- PERMISSION.pdf
- Adobe Scan Aug 16, 2023.pdf
Buyer community
Connect with other buyers and owners of SIDDHIVINAYAK โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching SIDDHIVINAYAK. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.