PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Amey ShilpMahaRERA P53100049555

by Amey Construction

Old Survey No 103/2B New Survey No 11/2/B Plot No 7, Wanlesswadi, 416416

Jun 2026
Possession
59.5%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Jun 2026) has passed with construction at 59.5%.

Official RERA facts

Registration
P53100049555
Status
New
Stage
Certificate Signed
Possession
June 2026
Construction
59.5% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Solid Waste Management And Disposal50%
Water conservation /Rain water harvestingdone
Electrical meter room, sub-station, receiving stationdone
Open Parkingdone

Building & registration

RERA registered
Feb 2023
Floors
5
Plot / CTS / survey no.
Old Survey No 103/2B New Survey No 11/2/B Plot No 7
Planning authority
Others
Approved layout land
253.45 sq.m
Land for this registration
253.45 sq.m
Permissible built-up area
507.2 sq.m
Registered office
Parijat Bunglow
Plot boundaries
North
Survey No 99
South
9 M Wide Road
East
Plot No 8
West
Plot No 6
Parking

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • KARNATAKA BANK LIMITED โ€” 84305
    IFSC KARB0000729
    Sangli Miraj Road, Sangli

Commencement Certificate documents

  • Amey Shilp Revised Commencement Certificate .pdf

Buyer community

Connect with other buyers and owners of Amey Shilp โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Amey Shilp. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.