Kamal RanjiniMahaRERA P53100052290
TP scheme 1, Final Plot No 69, Shivaji Nagar, 416410
- Behind schedule. Possession is due May 2027 but construction is only at 23.1%.
Official RERA facts
- Registration
- P53100052290
- Status
- New
- Stage
- Certificate Signed
- Possession
- May 2027
- Construction
- 23.1% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 24 Jul 2026).
Landowner
GOKHALE AND ASSOCIATES
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Aug 2023
- Floors
- 5
- Plot / CTS / survey no.
- TP scheme 1, Final Plot No 69
- Planning authority
- Others
- Approved layout land
- 735 sq.m
- Land for this registration
- 735 sq.m
- Permissible built-up area
- 2,836.08 sq.m
- Registered office
- DINKAR VILLA
- North
- Final Plot No 65
- South
- Final Ploit No73A 73B
- East
- Final Plot No 69-1
- West
- Road
Project bank account
The RERA-designated account this project's payments should go to โ verify before wiring any money.
- SARASWAT COOPERATIVE BANK LIMITED โ 143235IFSC SRCB0000167Laxmi Market, Highschool Road, Miraj
Commencement Certificate documents
- Commencement.pdf
- Commencement.pdf
Buyer community
Connect with other buyers and owners of Kamal Ranjini โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Kamal Ranjini. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.