Under construction

SAICHARAN HEIGHTSMahaRERA P53100053178

by ASHTANG DEVELOPERS

NEW SURVEY NO 137/A/2 & OLD SURVEY NO 185A/2, PLOT NO 26, WARANALI, SANGLI, 416415

Jun 2027
Possession
20.9%
Built
0
Complaints
30
Units
Caution
  • Behind schedule. Possession is due Jun 2027 but construction is only at 20.9%.

Official RERA facts

Registration
P53100053178
Status
New
Stage
Certificate Signed
Possession
June 2027originally June 2026
Construction
20.9% complete
Units sold
9 of 30

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Landowner

SURESH ISHWAR KALYANI

Possession extension history

  • EA25052621095Revised to June 2027

    We, Ashtang Developers, are promoter of the project Saicharan Heights, registered under MahaRERA vide registration number P53100053178. Sir the foresaid project was projected to be completed by 30/06/2026 but due to lesser response in bookings and technical problems raised in the project the project is now bound to be delayed. The project till date is about 80% completed which is also certified by the project architect in form 1 uploaded in MahaRERA portal. Currently out of total 30 units in the project, we have sold 09 units. Out of which 04 have already given their consent for extension of the project. We, Ashtang Developers, as promoter are obliged to complete the foresaid project and ensure that the rights and interests of our allottees remain intact. Once extension of the MahaRERA certificate is issued we shall complete the project till 30/06/2027. We, Ashtang Developers, assure that all the information given above is true and best of our knowledge. We hereby request you to grant us MahaRERA extension at the earliest so as to allow us to complete the project soon.

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started
E VEHICLE CHARGING POINT FOR TWO WHEELERSnot started

Building & registration

RERA registered
Oct 2023
Floors
9
Unit mix
23 res ยท 7 comm
Architect
NITIN VITTHALRAO SHINDE Vithhalrao Shinde
Plot / CTS / survey no.
NEW SURVEY NO 137/A/2 & OLD SURVEY NO 185A/2, PLOT NO 26
Planning authority
SMKC ,Sangli
Approved layout land
765.5 sq.m
Land for this registration
765.5 sq.m
Permissible built-up area
2,071.8 sq.m
Registered office
C/O JAGANNATH SALUNKE
Plot boundaries
North
ADJACENT PLOT NO 19
South
ROAD 9M WIDE
East
ROAD 30M WIDE
West
ADJACENT PLOT NOS 25 28 30
Parking

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • HDFC BANK โ€” 48681
    IFSC HDFC0000222
    VENKATESH SENATE, 640, KARMAVEER BHAURAO PATIL CHOWK SANGLI-MIRAJ ROAD, SANGLI-416416, MAHARASHTRA

Commencement Certificate documents

  • Commencement Certificate.pdf

Buyer community

Connect with other buyers and owners of SAICHARAN HEIGHTS โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SAICHARAN HEIGHTS. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.