Under construction

Siddhivinayak-LaxmiMahaRERA P53100055749

by Balaji Associates

CTS NO. 4221, Krushnali Vasahat, 416415

Sept 2026
Possession
64.1%
Built
0
Complaints
21
Units
Clean record

No delays, complaints or enforcement actions in the official disclosures we track.

Official RERA facts

Registration
P53100055749
Status
New
Stage
Certificate Signed
Possession
September 2026
Construction
64.1% complete
Units sold
10 of 21

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 24 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)70%
Storm Water Drains70%
Water conservation /Rain water harvesting50%
Energy managemcnt60%
Electrical meter room, sub-station, receiving station50%

Building & registration

RERA registered
Apr 2024
Floors
8
Unit mix
21 res ยท 0 comm
Architect
Ar Sachin G Kanoje
Plot / CTS / survey no.
CTS NO. 4221
Planning authority
Sangli-Miraj & Kupwad Municipal Corporation
Approved layout land
539.2 sq.m
Land for this registration
539.2 sq.m
Permissible built-up area
1,800.25 sq.m
Registered office
Omkar Apartment
Plot boundaries
North
Road
South
4222
East
4225
West
Road
Parking
11 four-wheeler

Project bank account

The RERA-designated account this project's payments should go to โ€” verify before wiring any money.

  • FEDERAL BANK โ€” 45638
    IFSC FDRL0001503
    Ground Floor, Siddhivinayak Forum Sangli Miraj Road, Vishrambagh, opposite Zilla Parishad, Sangli, M

Commencement Certificate documents

  • Commencement Certificate- Siddhivinayak-Laxmi.pdf
  • RERA Mail.pdf

Buyer community

Connect with other buyers and owners of Siddhivinayak-Laxmi โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Siddhivinayak-Laxmi. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 24 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.