Under construction

VRINDAVAN COMPLEX

by PATIL BUILDERS

OLD GAT NO 321 322-2 322-3 NEW GAT NO 322B 322C 322D 322E 322EE 322F, Palghar, 401102

High risk
  • Possession delayed ~2 yrs. Originally promised May 2019, now proposed Nov 2020 per the RERA filing.
  • Possession date passed. The proposed possession date (Nov 2020) has passed with construction at 90.9%.

Official RERA facts

Registration
P99000000827
Status
Ongoing
Stage
Certificate Signed
Possession
November 2020originally May 2019
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Water conservation /Rain water harvestingdone
Electrical meter room, sub-station, receiving stationdone
Open Parkingdone

Building & registration

RERA registered
Jul 2017
Floors
6

Buyer community

Connect with other buyers and owners of VRINDAVAN COMPLEX โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching VRINDAVAN COMPLEX. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.