Under construction

Surya Kirti Heights and TowerMahaRERA P99000003052

by S R & Shah Vala Associates

69 hissa no 5 71 hissa no 3 72 hissa no 10 72 Hissa no 11 73 hissa no 4, Virar, 401202

Dec 2026
Possession
81.4%
Built
6
Complaints
114
Units
High risk
  • Possession delayed ~8 yrs. Originally promised Dec 2018, now proposed Dec 2026 per the RERA filing.
  • 6 RERA complaints. 6 complaint records are disclosed against this project on MahaRERA.

Official RERA facts

Registration
P99000003052
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026originally December 2018
Construction
81.4% complete
Units sold
106 of 114

RERA complaint record6 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsdone
Landscaping & Tree Planting95%
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvesting95%
Fire protection and fire safety requirements95%
Electrical meter room, sub-station, receiving stationdone

Building & registration

RERA registered
Aug 2017
Floors
13
Unit mix
108 res ยท 6 comm

Buyer community

Connect with other buyers and owners of Surya Kirti Heights and Tower โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.