Under construction

SAI NAGARMahaRERA P99000006133

by SHUBHVASTU REALCON

1271B, -, 401208

Dec 2027
Possession
64%
Built
0
Complaints
81
Units
High risk
  • Possession delayed ~6 yrs. Originally promised Jun 2022, now proposed Dec 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.

Official RERA facts

Registration
P99000006133
Status
Ongoing
Stage
Certificate Signed
Possession
December 2027originally June 2022
Construction
64% complete
Units sold
75 of 81

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths70%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvesting50%
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parking12%

Building & registration

RERA registered
Aug 2017
Floors
5
Unit mix
81 res ยท 0 comm
Architect
SHAPE CONSULTANTS

Buyer community

Connect with other buyers and owners of SAI NAGAR โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SAI NAGAR. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.