All RERA projects
๐๏ธ
Under construction
VIVA CITY-A2MahaRERA P99000008341
by VIVA WINNER VENTURE RELATORS LLP
324, Virar West, 401303
Dec 2020
Possession
54.1%
Built
10
Complaints
0
Units
High risk
- Recovery warrant issued. MahaRERA has issued 1 recovery warrant against this project โ the strongest enforcement action on record.
- Possession delayed ~2 yrs. Originally promised Jun 2019, now proposed Dec 2020 per the RERA filing.
- 10 RERA complaints. 10 complaint records are disclosed against this project on MahaRERA.
- Possession date passed. The proposed possession date (Dec 2020) has passed with construction at 54.1%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2020 per the RERA filing.
Official RERA facts
- Registration
- P99000008341
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2020originally June 2019
- Construction
- 54.1% complete
- Units sold
- 0 of 0
RERA complaint record10 records
- ComplaintCC125038987 Nov 2025Raminder Singh vs VIVA WINNER VENTURE RELATORS LLP
- ComplaintCC1250287216 Aug 2025Raminder Singh vs VIVA WINNER VENTURE RELATORS LLProznama 3- conciliation Roznama.pdf on MahaRERA
- ComplaintCC00600000059150811 Aug 2024Poonam Pathare and Siddhesh Pathare vs Viva Winner Venture Realtors LLPOrder of Poonam Pathare - DFD (1).pdf on MahaRERA
- Recovery warrantCC00600000039707114 Aug 2023Raminder Singh vs Viva Group
- ComplaintCC00600000039707114 Aug 2023Raminder Singh vs Viva GroupRaminder Singh Or_0001signed.pdf on MahaRERA
- Misc. applicationCC00600000039707114 Aug 2023Raminder Singh vs Viva Group
- Misc. applicationCC00600000019716926 Jun 2021VINOD LOTAN KHAIRNAR vs VIVA GroupCC006_197169.pdf on MahaRERA
- ComplaintCC00600000019716926 Jun 2021VINOD LOTAN KHAIRNAR vs VIVA GroupCC006_197169.pdf on MahaRERA
- ComplaintCC0060000000900258 Jul 2019Ramimder Singh vs Viva Groupramimdar singh21112019184117_compressed.pdf on MahaRERA
- ComplaintCC00600000005690129 Nov 2018Nehal Nikhilkumar Thakkar & Nikhilkumar Thakkar vs Viva Winner Venture Realtors LLP5690101102019164856.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started
Building & registration
- RERA registered
- Aug 2017
- Floors
- 18
Buyer community
Connect with other buyers and owners of VIVA CITY-A2 โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching VIVA CITY-A2. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.