Under construction
KAILASH TOWER
SURVEY NO 72 H NO 1/1 1/3 3/1/1 10 11, VASAI, 401303
Dec 2024
Possession
90.9%
Built
5
Complaints
0
Units
High risk
- Possession delayed ~5 yrs. Originally promised Dec 2019, now proposed Dec 2024 per the RERA filing.
- Possession date passed. The proposed possession date (Dec 2024) has passed with construction at 90.9%.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2024 per the RERA filing.
Official RERA facts
- Registration
- P99000008452
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2024originally December 2019
- Construction
- 90.9% complete
- Units sold
- 0 of 0
RERA complaint record5 records
- ComplaintCC1250380131 Oct 2025CHANDRAPARAKASH KAILASHNATH YADAV vs KAILASH DEVELOPERSlop sr no39.pdf on MahaRERA
- Misc. applicationCC1250380131 Oct 2025CHANDRAPARAKASH KAILASHNATH YADAV vs KAILASH DEVELOPERS
- ComplaintCC00600000002381420 Mar 2018Rambabu sharma vs Partners of Kailash Developers -Mr Khetshi Patel, Mr Ramji Patel ,Mr.Paresh Chamaria and others23814 Rambabu Sharma Vs Kailash Developers.pdf on MahaRERA
- ComplaintCC00600000002311527 Jan 2018ANITA N DSOUZA/NELSON DSOUZA vs KHETSHI KARMSHI PATELCC 006 23115 Anita Dsouza Vs Kailash Developers.pdf on MahaRERA
- ComplaintCC00600000001203120 Nov 2017RAMITA SANJAY PANDEY / SANJAY DEONARAYAN PANDEY vs NANJI GOVINDA PATELCC006000000012031 Ramita Pandey.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths10%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)20%
Storm Water Drains70%
Landscaping & Tree Plantingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station40%
Aggregate area of recreational Open Spacenot started
Building & registration
- RERA registered
- Aug 2017
- Floors
- 14
Buyer community
Connect with other buyers and owners of KAILASH TOWER โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching KAILASH TOWER. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.