PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

SHUBHAM PARADISE

by ARHAM REALTORS

70/174/2,3,6, Vasai-Virar City (M Corp), 401303

Jun 2023
Possession
90.5%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Jun 2023) has passed with construction at 90.5%.

Official RERA facts

Registration
P99000008958
Status
Ongoing
Stage
Certificate Signed
Possession
June 2023
Construction
90.5% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths20%
Water Supply50%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drains10%
Landscaping & Tree Planting20%
Treatment And Disposal Of Sewage And Sullage Waterdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving station50%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Aug 2017
Floors
14

Buyer community

Connect with other buyers and owners of SHUBHAM PARADISE โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SHUBHAM PARADISE. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.