Under construction

TAALMahaRERA P99000010690

by Ace Property Developers

Survey no 88 Hissa no 1, Near Global City, 401303

Apr 2025
Possession
90.9%
Built
0
Complaints
55
Units
High risk
  • Possession delayed ~6 yrs. Originally promised Mar 2019, now proposed Apr 2025 per the RERA filing.
  • Possession date passed. The proposed possession date (Apr 2025) has passed with construction at 90.9%.

Official RERA facts

Registration
P99000010690
Status
Ongoing
Stage
Certificate Signed
Possession
April 2025originally March 2019
Construction
90.9% complete
Units sold
55 of 55

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone

Building & registration

RERA registered
Aug 2017
Floors
26
Unit mix
47 res ยท 8 comm
Architect
Ajay Wade and Associates

Buyer community

Connect with other buyers and owners of TAAL โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching TAAL. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.