Under construction

MATHURADHAMMahaRERA P99000011054

by RIDDHI SIDDHI REALTY

197, Umroli, 401404

Dec 2027
Possession
50.5%
Built
0
Complaints
80
Units
High risk
  • Possession delayed ~6 yrs. Originally promised Jul 2021, now proposed Dec 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.

Official RERA facts

Registration
P99000011054
Status
Ongoing
Stage
Certificate Signed
Possession
December 2027originally July 2021
Construction
50.5% complete
Units sold
33 of 80

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Aug 2017
Floors
104
Unit mix
56 res ยท 24 comm
Architect
SHRIKANT YEWLE

Buyer community

Connect with other buyers and owners of MATHURADHAM โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching MATHURADHAM. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.