Under construction
MAHAVIR RESIDENCYMahaRERA P99000012246
S NO 46 H NO 1, Virar West, 401303
Dec 2026
Possession
90.2%
Built
7
Complaints
65
Units
High risk
- Possession delayed ~6 yrs. Originally promised Jun 2021, now proposed Dec 2026 per the RERA filing.
- 7 RERA complaints. 7 complaint records are disclosed against this project on MahaRERA.
Official RERA facts
- Registration
- P99000012246
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2026originally June 2021
- Construction
- 90.2% complete
- Units sold
- 60 of 65
RERA complaint record7 records
- ComplaintCC00600000019850630 Sept 2021Mukesh V Gala, Nirmala N. Gala, Nenshi V. Gala, Velji B. Shah/Gala, Diwaliben V. Gala vs M/s. Mahaveer ConstructionOrder of Mukesh Gala (1).pdf on MahaRERA
- ComplaintCC00600000019600114 Feb 2021Mrs. Sangeeta Umesh Ved vs M/s. Mahavir ConstructionCommon Order of Mahavir Constructions- 3 complaints (1).pdf on MahaRERA
- ComplaintCC00600000019600214 Feb 20211) Mr. Navin Shankarlal Rajgor and 2) Mrs. Daksha Navin Rajgor vs M/s Mahavir ConstructionCommon Order of Mahavir Constructions- 3 complaints (1).pdf on MahaRERA
- ComplaintCC00600000019594614 Feb 20211. MRS. ARPITA BHAVESH SHAH 2. MR.BHAVESH RAMESH SHAH vs M/s. Mahavir ConstructionCommon Order of Mahavir Constructions- 3 complaints (1).pdf on MahaRERA
- Misc. applicationCC00600000019594614 Feb 20211. MRS. ARPITA BHAVESH SHAH 2. MR.BHAVESH RAMESH SHAH vs M/s. Mahavir Construction
- Misc. applicationCC00600000019600114 Feb 2021Mrs. Sangeeta Umesh Ved vs M/s. Mahavir Construction
- Misc. applicationCC00600000019600214 Feb 20211) Mr. Navin Shankarlal Rajgor and 2) Mrs. Daksha Navin Rajgor vs M/s Mahavir Construction
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths80%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsnot started
Landscaping & Tree Plantingdone
Treatment And Disposal Of Sewage And Sullage Water92%
Solid Waste Management And Disposal92%
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirements92%
Electrical meter room, sub-station, receiving station95%
Building & registration
- RERA registered
- Sept 2017
- Floors
- 17
- Unit mix
- 58 res ยท 7 comm
Buyer community
Connect with other buyers and owners of MAHAVIR RESIDENCY โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching MAHAVIR RESIDENCY. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.