MAHAVIR RESIDENCYMahaRERA P99000012246

by MAHAVIR CONSTRUCTIONS

S NO 46 H NO 1, Virar West, 401303

Dec 2026
Possession
90.2%
Built
7
Complaints
65
Units
High risk
  • Possession delayed ~6 yrs. Originally promised Jun 2021, now proposed Dec 2026 per the RERA filing.
  • 7 RERA complaints. 7 complaint records are disclosed against this project on MahaRERA.

Official RERA facts

Registration
P99000012246
Status
Ongoing
Stage
Certificate Signed
Possession
December 2026originally June 2021
Construction
90.2% complete
Units sold
60 of 65

RERA complaint record7 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths80%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsnot started
Landscaping & Tree Plantingdone
Treatment And Disposal Of Sewage And Sullage Water92%
Solid Waste Management And Disposal92%
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirements92%
Electrical meter room, sub-station, receiving station95%

Building & registration

RERA registered
Sept 2017
Floors
17
Unit mix
58 res ยท 7 comm

Buyer community

Connect with other buyers and owners of MAHAVIR RESIDENCY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching MAHAVIR RESIDENCY. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.