Under construction

RENUKA APPARTMENT TYPE GMahaRERA P99000013252

by AARYAN SINGH

GUT NO 210, UMROLI EAST, 401404

Apr 2027
Possession
50.7%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~8 yrs. Originally promised Apr 2019, now proposed Apr 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Apr 2027 per the RERA filing.

Official RERA facts

Registration
P99000013252
Status
Ongoing
Stage
Certificate Signed
Possession
April 2027originally April 2019
Construction
50.7% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Sept 2017
Floors
6

Buyer community

Connect with other buyers and owners of RENUKA APPARTMENT TYPE G โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching RENUKA APPARTMENT TYPE G. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.