SAI BHAKTI COMPLEXMahaRERA P99000013389
S NO 1023 H NO 1 AND 2/19, PALGHAR, 401404
Dec 2027
Possession
81.5%
Built
1
Complaints
77
Units
High risk
- Possession delayed ~4 yrs. Originally promised Dec 2023, now proposed Dec 2027 per the RERA filing.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.
Official RERA facts
- Registration
- P99000013389
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2027originally December 2023
- Construction
- 81.5% complete
- Units sold
- 26 of 77
RERA complaint record1 record
- ComplaintCC00600000005621515 Sept 2018Hemendra Madhusudan Bhat vs Sai Bhakti DevelopersCC 006 56215 (1).pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths50%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lighting40%
Building & registration
- RERA registered
- Oct 2017
- Floors
- 4
- Unit mix
- 67 res ยท 10 comm
Buyer community
Connect with other buyers and owners of SAI BHAKTI COMPLEX โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching SAI BHAKTI COMPLEX. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.