SWAPNLOK RESIDENCY PHASE II

by SHIV SAI DEVELOPERS

GUT NO 462/B, umroli, 401404

Dec 2027
Possession
4.5%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~8 yrs. Originally promised Jan 2020, now proposed Dec 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.
Vasai–VirarValue

The western line's volume market — dense affordable towers past Mira Road.

Growth drivers:
Suburban rail quadrupling, coastal-road extensions, MMR's biggest affordable pipeline.
Who buys here:
Budget-first buyers who commute the western line.

PropPin area guide — editorial, not a RERA disclosure.

Official RERA facts

Registration
P99000015323
Status
New
Stage
Certificate Signed
Possession
December 2027originally January 2020
Construction
4.5% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingdone

Building & registration

RERA registered
Feb 2018
Floors
4

Buyer community

Connect with other buyers and owners of SWAPNLOK RESIDENCY PHASE II — compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet — start one and connect with the next buyer researching SWAPNLOK RESIDENCY PHASE II. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.