PARASNATH TOWNSHIPMahaRERA P99000015590

by SHREENATH ENTERPRISES

392 393 394A 394B, PANCHALI GRAM PANCHAYAT, 401404

Mar 2028
Possession
109.8%
Built
0
Complaints
193
Units
High risk
  • Possession delayed ~8 yrs. Originally promised Mar 2020, now proposed Mar 2028 per the RERA filing.

Official RERA facts

Registration
P99000015590
Status
New
Stage
Certificate Signed
Possession
March 2028originally March 2020
Construction
109.8% complete
Units sold
138 of 193

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths95%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drains85%
Street Lightingnot started
Solid Waste Management And Disposalnot started
Electrical meter room, sub-station, receiving station50%

Building & registration

RERA registered
Mar 2018
Floors
8
Unit mix
130 res ยท 63 comm

Buyer community

Connect with other buyers and owners of PARASNATH TOWNSHIP โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching PARASNATH TOWNSHIP. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.