All RERA projects
๐๏ธ
Under construction
NIRVANA ECO HOMESMahaRERA P99000015865
268, PALGHAR, 401404
Dec 2024
Possession
22.7%
Built
0
Complaints
0
Units
High risk
- Possession date passed. The proposed possession date (Dec 2024) has passed with construction at 22.7%.
Official RERA facts
- Registration
- P99000015865
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- December 2024
- Construction
- 22.7% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 21 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsdone
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)40%
Storm Water Drainsnot started
Landscaping & Tree Planting75%
Street Lightingdone
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving station30%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started
Building & registration
- RERA registered
- Mar 2018
- Floors
- 6
Buyer community
Connect with other buyers and owners of NIRVANA ECO HOMES โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching NIRVANA ECO HOMES. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.