PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Nine Star Residency - Imperia

by M/s A.K. Developers

Gut No - 246/2/1, Palghar, 401102

High risk
  • Possession date passed. The proposed possession date (Mar 2022) has passed with construction at 48.2%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2022 per the RERA filing.

Official RERA facts

Registration
P99000015888
Status
New
Stage
Certificate Signed
Possession
March 2022
Construction
48.2% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths60%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Mar 2018
Floors
5

Buyer community

Connect with other buyers and owners of Nine Star Residency - Imperia โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Nine Star Residency - Imperia. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.