Under construction
MIRAYAMahaRERA P99000016401
PLOT NO 7A, SURVEY NO 827/3PT, MAHIM, 401404
Jun 2022
Possession
49.1%
Built
0
Complaints
0
Units
High risk
- Possession delayed ~1 yr. Originally promised Dec 2020, now proposed Jun 2022 per the RERA filing.
- Possession date passed. The proposed possession date (Jun 2022) has passed with construction at 49.1%.
Official RERA facts
- Registration
- P99000016401
- Status
- Ongoing
- Stage
- Certificate Signed
- Possession
- June 2022originally December 2020
- Construction
- 49.1% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 21 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)30%
Storm Water Drainsnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Building & registration
- RERA registered
- May 2018
- Floors
- 6
Buyer community
Connect with other buyers and owners of MIRAYA โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching MIRAYA. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.