UNIQUE TOWERMahaRERA P99000019513

by Unique Realtors

285 287, JAMBUPADA PHATA, 401404

May 2027
Possession
12.7%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~4 yrs. Originally promised May 2023, now proposed May 2027 per the RERA filing.
  • Behind schedule. Possession is due May 2027 but construction is only at 12.7%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due May 2027 per the RERA filing.

Official RERA facts

Registration
P99000019513
Status
New
Stage
Certificate Signed
Possession
May 2027originally May 2023
Construction
12.7% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Feb 2019
Floors
9

Buyer community

Connect with other buyers and owners of UNIQUE TOWER โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching UNIQUE TOWER. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.