PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

ONE STAR DEVELOPERSMahaRERA P99000020003

by ISHTIYAKAAHMAD BAITULLAH KHAN

S. NO. 51, NR NEW LIFE EDUCATION ENGLISH SCHOOL, 401208

Sept 2022
Possession
0%
Built
0
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Sept 2022) has passed with construction at 0%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Sept 2022 per the RERA filing.

Official RERA facts

Registration
P99000020003
Status
New
Stage
Certificate Signed
Possession
September 2022
Construction
0% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 23 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Mar 2019
Floors
9

Buyer community

Connect with other buyers and owners of ONE STAR DEVELOPERS โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ONE STAR DEVELOPERS. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.