Rustomjee Virar Avenue L1-L2 and L4 Wing KMahaRERA P99000020235
by KEYSTONE INFRASTRUCTURE PRIVATE LIMITED
pt of Avenue L1 L2 L4 being pt of larger layout being sy no 5 5B 5D 5F 5G of village Dongre, Avenue L4, 401303
- Possession date passed. The proposed possession date (Sept 2024) has passed with construction at 50%.
- Promised amenities not started. Landscaped Garden, Sports / Jogging are at 0% build with possession due Sept 2024 per the RERA filing.
Official RERA facts
- Registration
- P99000020235
- Status
- New
- Stage
- Certificate Signed
- Possession
- September 2024originally September 2023
- Construction
- 50% complete
- Units sold
- 0 of 0
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 21 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Building & registration
- RERA registered
- Mar 2019
- Floors
- 18
Buyer community
Connect with other buyers and owners of Rustomjee Virar Avenue L1-L2 and L4 Wing K โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Rustomjee Virar Avenue L1-L2 and L4 Wing K. Real notes from real buyers beat any brochure.
Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.