Under construction

NILSA HOMESMahaRERA P99000021644

by NILAM RAMAKANT SANKHE

S N 73B OLD SN373PT, Katkar, 401501

Dec 2030
Possession
40.9%
Built
0
Complaints
35
Units
High risk
  • Possession delayed ~6 yrs. Originally promised May 2025, now proposed Dec 2030 per the RERA filing.

Official RERA facts

Registration
P99000021644
Status
New
Stage
Certificate Signed
Possession
December 2030originally May 2025
Construction
40.9% complete
Units sold
5 of 35

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Jul 2019
Floors
8
Unit mix
35 res ยท 0 comm
Architect
Nishant Patil Vastu Shilp

Buyer community

Connect with other buyers and owners of NILSA HOMES โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.