Under construction

Veena Samrajya-Sector-VIIIMahaRERA P99000021726

by Veena Developers

942/2/10, Palghar West, 401404

Mar 2027
Possession
32.7%
Built
6
Complaints
1,588
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Dec 2023, now proposed Mar 2027 per the RERA filing.
  • 6 RERA complaints. 6 complaint records are disclosed against this project on MahaRERA.
  • Behind schedule. Possession is due Mar 2027 but construction is only at 32.7%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Mar 2027 per the RERA filing.

Official RERA facts

Registration
P99000021726
Status
New
Stage
Certificate Signed
Possession
March 2027originally December 2023
Construction
32.7% complete
Units sold
506 of 1588

RERA complaint record6 records

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths60%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drains50%
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingnot started
Energy managemcntnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Jul 2019
Floors
10
Unit mix
1588 res ยท 0 comm
Architect
Ajay Wade & Associates

Buyer community

Connect with other buyers and owners of Veena Samrajya-Sector-VIII โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Veena Samrajya-Sector-VIII. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.