All RERA projects
๐๏ธ
High risk
- Possession delayed ~3 yrs. Originally promised Aug 2025, now proposed Dec 2028 per the RERA filing.
Official RERA facts
- Registration
- P99000022165
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2028originally August 2025
- Construction
- 60.6% complete
- Units sold
- 38 of 209
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 20 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started
Building & registration
- RERA registered
- Sept 2019
- Floors
- 10
- Unit mix
- 209 res ยท 0 comm
- Architect
- Roshan Rajendra Patil
Buyer community
Connect with other buyers and owners of MITHILA COMPLEX โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching MITHILA COMPLEX. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.