All RERA projects
๐๏ธ
Under construction
YUKTAM AVENUE WING A AND BMahaRERA P99000022611
by YUKTAM INFRA & REALTORS PVT LTD
Gut 113, Palghar, 401501
Jun 2028
Possession
38.2%
Built
0
Complaints
54
Units
High risk
- Possession delayed ~5 yrs. Originally promised Feb 2023, now proposed Jun 2028 per the RERA filing.
Official RERA facts
- Registration
- P99000022611
- Status
- New
- Stage
- Certificate Signed
- Possession
- June 2028originally February 2023
- Construction
- 38.2% complete
- Units sold
- 0 of 54
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 21 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Building & registration
- RERA registered
- Oct 2019
- Floors
- 5
- Unit mix
- 47 res ยท 7 comm
Buyer community
Connect with other buyers and owners of YUKTAM AVENUE WING A AND B โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching YUKTAM AVENUE WING A AND B. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.