Under construction

RAAJLAXMI TOWERSMahaRERA P99000022706

by RAJLAXMI DEVELOPERS

SURVEY NO 29B H NO 73, 74, 76, AMBAWADI BUNGLOW SCHEME, 401208

Dec 2025
Possession
0%
Built
1
Complaints
0
Units
High risk
  • Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 0%.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2025 per the RERA filing.

Official RERA facts

Registration
P99000022706
Status
New
Stage
Certificate Signed
Possession
December 2025
Construction
0% complete
Units sold
0 of 0

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths50%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Community Buildingsnot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Oct 2019
Floors
109

Buyer community

Connect with other buyers and owners of RAAJLAXMI TOWERS โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching RAAJLAXMI TOWERS. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 23 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.