Under construction

Vrindavan City D WingMahaRERA P99000023650

by SRA PROJECT DEVELOPERS PRIVATE LIMITED

28/3, 30/4, 28/3/1, 30/3, Next to Narmada Vihar, 401501

Oct 2026
Possession
60.9%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~3 yrs. Originally promised Oct 2023, now proposed Oct 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Oct 2026 per the RERA filing.

Official RERA facts

Registration
P99000023650
Status
New
Stage
Certificate Signed
Possession
October 2026originally October 2023
Construction
60.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths50%
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Dec 2019
Floors
5
Architect
Nishant Patil

Buyer community

Connect with other buyers and owners of Vrindavan City D Wing โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Vrindavan City D Wing. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.