PropPin
All RERA projects
๐Ÿ—๏ธ
Under construction

Sunteck MaxxWorld 3, Tivri, Naigaon EastMahaRERA P99000024111

by Sunteck Realty Limited

51/1, 51/4, 51/5, 51/6, 51/7, 51/8, 51/9, 51/10, 51/11, 52/1, 52/3, 52/5-1, 52/5-2, 54/4-2, 54/6, 54/7-2, 55/4, Tivri, 401208

Dec 2025
Possession
85.5%
Built
6
Complaints
0
Units
High risk
  • 6 RERA complaints. 6 complaint records are disclosed against this project on MahaRERA.
  • Possession date passed. The proposed possession date (Dec 2025) has passed with construction at 85.5%.

Official RERA facts

Registration
P99000024111
Status
New
Stage
Certificate Signed
Possession
December 2025
Construction
85.5% complete
Units sold
0 of 0

RERA complaint record6 records

  • ComplaintCC124003314 Oct 2024
    Chandramani Jangde vs Sunteck Realty Limited
    Final Order CC12400331.pdf on MahaRERA
  • ComplaintCC00600000057081218 Jun 2024
    Sunteck Realty Limited vs mr. Mohhmmad Rais Mohammad Idris Manihar
    P99000024111.pdf on MahaRERA
  • Misc. applicationCC00600000057081218 Jun 2024
    Sunteck Realty Limited vs mr. Mohhmmad Rais Mohammad Idris Manihar
  • ComplaintCC00600000050047116 May 2024
    Leena Pedru Fernandes vs Sunteck Realty Ltd and 3 Ors
  • ComplaintCC00600000039661412 Jul 2023
    Sunteck Realty Limited vs Mr. Rohit Kumar Tewari
    P99000024111.pdf on MahaRERA
  • Misc. applicationCC00600000039661412 Jul 2023
    Sunteck Realty Limited vs Mr. Rohit Kumar Tewari

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths85%
Water Supply95%
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drains98%
Landscaping & Tree Planting75%
Street Lighting50%
Community Buildings85%
Treatment And Disposal Of Sewage And Sullage Water90%
Solid Waste Management And Disposal90%
Water conservation /Rain water harvesting90%
Energy managemcntnot started
Fire protection and fire safety requirements90%
Electrical meter room, sub-station, receiving station80%
Aggregate area of recreational Open Spacenot started
Open Parkingnot started

Building & registration

RERA registered
Jan 2020
Floors
24
Public authority
Vasai Virar City Municipal Corporation (VVCMC)

Buyer community

Connect with other buyers and owners of Sunteck MaxxWorld 3, Tivri, Naigaon East โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching Sunteck MaxxWorld 3, Tivri, Naigaon East. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.