Under construction

SAVERA COMPLEXMahaRERA P99000024115

by UVA INFRA

GUT NO 144, S S PARK, 401404

Dec 2027
Possession
21.8%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Dec 2023, now proposed Dec 2027 per the RERA filing.
  • Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Dec 2027 per the RERA filing.

Official RERA facts

Registration
P99000024115
Status
New
Stage
Certificate Signed
Possession
December 2027originally December 2023
Construction
21.8% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Community Buildingsnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started

Building & registration

RERA registered
Jan 2020
Floors
5

Buyer community

Connect with other buyers and owners of SAVERA COMPLEX โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching SAVERA COMPLEX. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.