Under construction

K K PARK - PHASE IMahaRERA P99000024440

by K.K.CONSTRUCTION

70/6 ,70/7, NEAR DANDEKAR COLLEGE, 401404

Dec 2027
Possession
70%
Built
0
Complaints
224
Units
Caution
  • Possession delayed ~2 yrs. Originally promised Dec 2025, now proposed Dec 2027 per the RERA filing.

Official RERA facts

Registration
P99000024440
Status
New
Stage
Certificate Signed
Possession
December 2027originally December 2025
Construction
70% complete
Units sold
97 of 224

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 21 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)80%
Landscaping & Tree Planting70%
Street Lighting75%
Treatment And Disposal Of Sewage And Sullage Water80%
Solid Waste Management And Disposal85%
Fire protection and fire safety requirements85%
Electrical meter room, sub-station, receiving station85%
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Feb 2020
Floors
9
Unit mix
224 res ยท 0 comm
Architect
L Madan

Buyer community

Connect with other buyers and owners of K K PARK - PHASE I โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching K K PARK - PHASE I. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 21 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.