Under construction

GREG MARSH RESIDENCYMahaRERA P99000024941

by Shree Greg Marsh Realty

SNO85,HNO 5, SNO86, HNO1/2,2/2,3,S NO 87,H NO4, 5/1,5/2, 6A,6B, SNO 90 HNO 1 TO 13, 14A, 14B, 16, SNO 91 HNO 2, 3, 6 TO 8, SNO 92, HNO 3,9A, 9B, 10-19, 21, 22, 23, SNO 96 HNO 2, 3, 6 TO 12, SNO 95 HNO 4, 10, VASAI EAST, 401208

Dec 2021
Possession
90.9%
Built
0
Complaints
0
Units
Caution
  • Possession date passed. The proposed possession date (Dec 2021) has passed with construction at 90.9%.

Official RERA facts

Registration
P99000024941
Status
New
Stage
Certificate Signed
Possession
December 2021
Construction
90.9% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Street Lightingdone
Solid Waste Management And Disposaldone
Water conservation /Rain water harvestingdone
Electrical meter room, sub-station, receiving stationdone
Aggregate area of recreational Open Spacedone

Building & registration

RERA registered
Mar 2020
Floors
6

Buyer community

Connect with other buyers and owners of GREG MARSH RESIDENCY โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.