All RERA projects
๐๏ธ
Under construction
SHALIGRAM TOWNSHIPMahaRERA P99000025137
by SHREE YASHOMATI BUILDERS DEVELOPERS
GUT NO 137, PADGHE, 401501
Jun 2027
Possession
34.5%
Built
6
Complaints
47
Units
High risk
- Possession delayed ~2 yrs. Originally promised Dec 2024, now proposed Jun 2027 per the RERA filing.
- 6 RERA complaints. 6 complaint records are disclosed against this project on MahaRERA.
- Behind schedule. Possession is due Jun 2027 but construction is only at 34.5%.
- Promised amenities not started. Clubhouse, Landscaped Garden are at 0% build with possession due Jun 2027 per the RERA filing.
Official RERA facts
- Registration
- P99000025137
- Status
- New
- Stage
- Certificate Signed
- Possession
- June 2027originally December 2024
- Construction
- 34.5% complete
- Units sold
- 18 of 47
RERA complaint record6 records
- ComplaintCC1250064223 Feb 2025Dinesh Roshanlal Jain vs SHREE YASHOMATI BUILDERS DEVELOPERS
- ComplaintCC00600000054074711 Jun 2024KUMUD ARJUN BHINGANIYA vs UMESH NARENDRA RAI540747.pdf on MahaRERA
- Misc. applicationCC00600000054074711 Jun 2024KUMUD ARJUN BHINGANIYA vs UMESH NARENDRA RAI
- ComplaintCC00600000048031330 Apr 2024DURGA PRASAD RAJNARAYAN SHARMA vs YASHWANT TEJBAHADUR SINGHCC006000000480313.pdf on MahaRERA
- ComplaintCC0060000003029949 Dec 2022DURGA PRASAD RAJNARAYAN SHARMA vs YASHWANT TEJBAHADUR SINGH8o.pdf on MahaRERA
- ComplaintCC00600000023125321 May 2022sanjay ramkumar gupta vs Umesh RaiSANJAY RAMKUMAR GUPTA.pdf on MahaRERA
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Community Buildingsnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Spacenot started
Open Parkingnot started
Building & registration
- RERA registered
- Mar 2020
- Floors
- 4
- Unit mix
- 29 res ยท 18 comm
Buyer community
Connect with other buyers and owners of SHALIGRAM TOWNSHIP โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching SHALIGRAM TOWNSHIP. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.