All RERA projects
๐๏ธ
High risk
- Possession delayed ~4 yrs. Originally promised Nov 2023, now proposed Jun 2027 per the RERA filing.
Official RERA facts
- Registration
- P99000025455
- Status
- New
- Stage
- Certificate Signed
- Possession
- June 2027originally November 2023
- Construction
- 73.9% complete
- Units sold
- 66 of 106
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 20 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpaths50%
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drains40%
Landscaping & Tree Planting30%
Street Lightingnot started
Water conservation /Rain water harvesting40%
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started
Building & registration
- RERA registered
- Jun 2020
- Floors
- 7
- Unit mix
- 101 res ยท 5 comm
- Architect
- ANJALIS ASSOCIATES
Buyer community
Connect with other buyers and owners of PARIVAR RESIDENCY โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching PARIVAR RESIDENCY. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 20 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.