PRITHVI ANAND KUBER COMPLEXMahaRERA P99000025647

by Prithvi Anand Housing and Land Developers

Survey No 54/2, Near St. John College, 401404

Jul 2026
Possession
88.6%
Built
1
Complaints
408
Units
Caution
  • Possession delayed ~1 yr. Originally promised Jun 2025, now proposed Jul 2026 per the RERA filing.

Official RERA facts

Registration
P99000025647
Status
New
Stage
Certificate Signed
Possession
July 2026originally June 2025
Construction
88.6% complete
Units sold
407 of 408

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drainsdone
Landscaping & Tree Plantingdone
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsdone
Electrical meter room, sub-station, receiving stationdone

Building & registration

RERA registered
Jul 2020
Floors
12
Unit mix
357 res ยท 51 comm
Architect
Ambre Gangatullu and associates

Buyer community

Connect with other buyers and owners of PRITHVI ANAND KUBER COMPLEX โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching PRITHVI ANAND KUBER COMPLEX. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.