Under construction

ANANT APARTMENTMahaRERA P99000026731

by ANANTA DEVELOPERS

GUT NO 234 AND GUT NO 240, ALLYALI, 401404

Dec 2026
Possession
84.5%
Built
1
Complaints
34
Units
High risk
  • Possession delayed ~4 yrs. Originally promised Dec 2022, now proposed Dec 2026 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P99000026731
Status
New
Stage
Certificate Signed
Possession
December 2026originally December 2022
Construction
84.5% complete
Units sold
18 of 34

RERA complaint record1 record

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)done
Storm Water Drains50%
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving station50%
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Oct 2020
Floors
6
Unit mix
30 res ยท 4 comm
Architect
EMPIRE ARCHITECTS

Buyer community

Connect with other buyers and owners of ANANT APARTMENT โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching ANANT APARTMENT. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.