Under construction

RAMESH HEIGHTS PHASE 1MahaRERA P99000026830

by SAI VIDYA CONSTRUCTION

SURVEY NO.7 HISSA NO.1A,2A , SURVEY NO.8, NILEMORE, 401203

Dec 2026
Possession
71.4%
Built
0
Complaints
65
Units
Caution
  • Possession delayed ~3 yrs. Originally promised Jun 2024, now proposed Dec 2026 per the RERA filing.

Official RERA facts

Registration
P99000026830
Status
New
Stage
Certificate Signed
Possession
December 2026originally June 2024
Construction
71.4% complete
Units sold
57 of 65

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpaths95%
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)90%
Landscaping & Tree Planting95%
Street Lightingnot started
Water conservation /Rain water harvestingdone
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving station90%
Aggregate area of recreational Open Spacenot started

Building & registration

RERA registered
Oct 2020
Floors
9
Unit mix
65 res ยท 0 comm
Architect
ABHAY RAUT

Buyer community

Connect with other buyers and owners of RAMESH HEIGHTS PHASE 1 โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching RAMESH HEIGHTS PHASE 1. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.