Under construction
Thakur Nagari Building No 6MahaRERA P99000026873
61/1/4/2, Pasthal, 401501
Jun 2027
Possession
64.1%
Built
0
Complaints
58
Units
High risk
- Possession delayed ~3 yrs. Originally promised Jun 2024, now proposed Jun 2027 per the RERA filing.
- Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2027 per the RERA filing.
Official RERA facts
- Registration
- P99000026873
- Status
- New
- Stage
- Certificate Signed
- Possession
- June 2027originally June 2024
- Construction
- 64.1% complete
- Units sold
- 58 of 58
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 22 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Building & registration
- RERA registered
- Nov 2020
- Floors
- 5
- Unit mix
- 58 res ยท 0 comm
- Architect
- Nishant Patil
Buyer community
Connect with other buyers and owners of Thakur Nagari Building No 6 โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching Thakur Nagari Building No 6. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.