Under construction

PARAMOUNT ENCLAVE BUILDING NO 2 TYPE D A WINGMahaRERA P99000027349

by SKYLINE DEVELOPERS

SURVEY NO 1023/7, PALGHAR WEST, 401404

Dec 2027
Possession
81.8%
Built
0
Complaints
0
Units
High risk
  • Possession delayed ~5 yrs. Originally promised Jun 2023, now proposed Dec 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2027 per the RERA filing.

Official RERA facts

Registration
P99000027349
Status
New
Stage
Certificate Signed
Possession
December 2027originally June 2023
Construction
81.8% complete
Units sold
0 of 0

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsdone
Water Supplydone
Sewerage (Chamber, Lines, Septic Tank , STP)30%
Storm Water Drainsdone
Landscaping & Tree Plantingnot started
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving station50%

Building & registration

RERA registered
Dec 2020
Floors
5

Buyer community

Connect with other buyers and owners of PARAMOUNT ENCLAVE BUILDING NO 2 TYPE D A WING โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching PARAMOUNT ENCLAVE BUILDING NO 2 TYPE D A WING. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.