All RERA projects
๐๏ธ
Under construction
PARASNATH NAGARIMahaRERA P99000027533
154/B, UMROLI RLY STN, 401404
Dec 2027
Possession
53.6%
Built
0
Complaints
77
Units
High risk
- Possession delayed ~5 yrs. Originally promised Jun 2023, now proposed Dec 2027 per the RERA filing.
Official RERA facts
- Registration
- P99000027533
- Status
- New
- Stage
- Certificate Signed
- Possession
- December 2027originally June 2023
- Construction
- 53.6% complete
- Units sold
- 43 of 77
RERA complaint record0 records
No complaints disclosed on MahaRERA (checked 22 Jul 2026).
Amenities & common facilities
Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.
Internal Roads & Footpathsdone
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drains95%
Street Lightingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Aggregate area of recreational Open Space10%
Open Parkingnot started
Building & registration
- RERA registered
- Dec 2020
- Floors
- 6
- Unit mix
- 50 res ยท 27 comm
Buyer community
Connect with other buyers and owners of PARASNATH NAGARI โ compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.
No topics yet โ start one and connect with the next buyer researching PARASNATH NAGARI. Real notes from real buyers beat any brochure.
Any possession update?Construction quality & site-visit notesAnyone else booked here?What price / quote did you get?Resale value & rental yield?Home loan & bank approvalsAmenities โ what's actually built?Society formation & maintenance
Start a discussionData sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.