High risk
  • Possession delayed ~3 yrs. Originally promised Sept 2024, now proposed Jun 2027 per the RERA filing.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Jun 2027 per the RERA filing.

Official RERA facts

Registration
P99000028045
Status
New
Stage
Certificate Signed
Possession
June 2027originally September 2024
Construction
80% complete
Units sold
14 of 19

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 20 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Landscaping & Tree Plantingnot started
Water conservation /Rain water harvestingnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
Jan 2021
Floors
5
Unit mix
19 res ยท 0 comm
Architect
Roshan Patil & Associates

Buyer community

Connect with other buyers and owners of VASTU IMPRESSA B-WING โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.