Under construction

NIDHI HOTELMahaRERA P99000029176

by LALIT NAGINDAS DOSHI

S NO 38 H NO 4, SATIVALI, 401208

Dec 2026
Possession
28%
Built
0
Complaints
9
Units
High risk
  • Behind schedule. Possession is due Dec 2026 but construction is only at 28%.
  • Promised amenities not started. Landscaped Garden is at 0% build with possession due Dec 2026 per the RERA filing.

Official RERA facts

Registration
P99000029176
Status
New
Stage
Certificate Signed
Possession
December 2026
Construction
28% complete
Units sold
8 of 9

RERA complaint record0 records

No complaints disclosed on MahaRERA (checked 22 Jul 2026).

Amenities & common facilities

Promised amenities and how complete each one is, from the promoter's MahaRERA disclosure.

Internal Roads & Footpathsnot started
Water Supplynot started
Sewerage (Chamber, Lines, Septic Tank , STP)not started
Storm Water Drainsnot started
Landscaping & Tree Plantingnot started
Street Lightingnot started
Treatment And Disposal Of Sewage And Sullage Waternot started
Solid Waste Management And Disposalnot started
Water conservation /Rain water harvestingnot started
Fire protection and fire safety requirementsnot started
Electrical meter room, sub-station, receiving stationnot started
Open Parkingnot started

Building & registration

RERA registered
May 2021
Floors
5
Unit mix
0 res ยท 9 comm

Buyer community

Connect with other buyers and owners of NIDHI HOTEL โ€” compare quotes, swap site-visit notes and possession updates, and check construction quality before you commit. No brokers, no sales pitch.

No topics yet โ€” start one and connect with the next buyer researching NIDHI HOTEL. Real notes from real buyers beat any brochure.

Start a discussion

Data sourced from the official MahaRERA portal; complaints last synced 22 Jul 2026. PropPin surfaces public disclosures verbatim and is not affiliated with MahaRERA.